2019 Capital Improvement Projects

Street Reconstruction Projects

  • Buena Vista Drive, N Walker Way - Ruby Lane
  • Clara Street, Gerald Ave, Ernest Ave, Elizabeth Lane, Elizabeth Ct, Scheuerell Lane
  • Roland St, Allen Ave, Williamson Ave
  • Broadway Drive, Steven Street, Blazer Ct, Dickson Drive
  • Pine Street, N Pine Street, Vandenburg Street, Jerico Lane
  • Surrey Drive, Schuster Road

Estimated Timelines for Projects (last updated 5/23/19)

Buena Vista Drive, N Walker Way to Ruby Lane - on time

This will be a Ruby Lane Reconstruction & N Walker Way Rehabilitation Project. Work has begun on Ruby Lane. Work on N Walker Way and Buena Vista Drive from N Walker Way to Garnet Drive will not start until June 12.

Clara Street, Gerald Ave, Ernest Ave, Elizabeth Lane, Elizabeth Ct, Scheuerell Lane - on time

Work has started on Clara St and Gerald Ave and will continue until June 12. Ernest, Elizabeth and Scheuerell construction will start after June 12.

Roland St, Allen Ave, Williamson Ave -scheduled

This reconstruction project is tentatively scheduled to start on July 1. 

Broadway Drive, Steven Street, Blazer Ct, Dickson Drive - scheduled, delayed

The contractor has pushed back the start date to the week of May 27. The contractor has decided to start moving equipment in and starting construction on May 28. They will be removing the existing mailboxes and placing temporary mailboxes near the park at the intersection of Steven street and Broadway drive. They are planning on starting on the storm sewer on Steven street mid to late next week (5/27 - 5/31).   

Pine Street, N Pine Street, Vandenburg Street, Jerico Lane - scheduled

This project is tentatively scheduled to start after July 1. 

Surrey Drive, Schuster Road - scheduled

This project is tentatively scheduled to start after July 1.